Visual Studio - Delivery Plan RRS feed

  • Question

  • Questions/Issues with Delivery Plan in Visual Studio's

    1. How can you get the names of the markers in the Delivery Plans to display without having to click on them?So they display when a user get's to that page?  

    2. How can you pull in the cards from the Kanbon board into the delivery plan? According to my research, these two should be interactive? If they are not interactive, how can you create new note cards in the delivery plans?

    Please contact me for screen shots. I tried to attach images, but received an error I am unable to until you verify my account? 

    Thank you, 

    pmf4287

    Monday, June 5, 2017 5:51 PM

All replies

  • Hi pmf4287,

    Thank you for reaching out. For Markers, we do not have the capability to display the Markers without a click to activate yet. Our initial design choice was to avoid noise, so we made them available upon click. I understand your feedback for an option to configure this.

    The Delivery Plan is based on the iteration path because we render work on a calendar element based on the sprint it is expected to be delivered/shipped. For this version, if Kanban teams want to leverage Plans, they will have to opt into the iterations/sprints defined in their project and assign work into the appropriate iteration paths.

    Please reach out again if you have any other questions.

    Best,

    Sondra Batbold