  • What does the cumulative flow tell you, I understand the new, approved, committed work item counts. But type of trend do you want to see? How do you interpret the graph? What does it tell you?
    Friday, April 4, 2014 3:39 PM

Answers

  • The Requirements progress is viewed on Cumulative Flow Diagram . It gives the overview about In Progress work at different stages of Requirements.


    Jahangeer

    Friday, April 4, 2014 6:38 PM
  • I have not found this feature to be over helpful so far.  But, I could see it being useful on a project that is using Kanban or is trying to close out a lot of work items.  This article looks good on how to use cumulative flow diagrams from one of the founders of Kanban, Dave Anderson.

    http://leonardwoody.com

    Wednesday, April 9, 2014 11:55 PM

All replies

  • The Requirements progress is viewed on Cumulative Flow Diagram . It gives the overview about In Progress work at different stages of Requirements.


    Jahangeer

    Friday, April 4, 2014 6:38 PM
  • I have not found this feature to be over helpful so far.  But, I could see it being useful on a project that is using Kanban or is trying to close out a lot of work items.  This article looks good on how to use cumulative flow diagrams from one of the founders of Kanban, Dave Anderson.

    http://leonardwoody.com

    Wednesday, April 9, 2014 11:55 PM