  • Hello,

    In Project Server 2010 PWA,  I had many tasks in my work that I have deleted and still displayed but barred.
    I want to remove completely that tasks in order to not be displayed in my work view.

    Who could help me please !

    Thanks.

    Friday, November 2, 2012 10:05 AM

Answers

  • Hi,

    you need to submit them. Afterwards, your PM has to approve and publish. Did this happen?

    Barbara

    • Proposed as answer by Justin Marks (MSFT) Monday, November 5, 2012 10:58 PM
    • Marked as answer by w.benamor Tuesday, November 27, 2012 2:30 PM
    Friday, November 2, 2012 12:54 PM

All replies

  • Hi,

    you need to submit them. Afterwards, your PM has to approve and publish. Did this happen?

    Barbara

    • Proposed as answer by Justin Marks (MSFT) Monday, November 5, 2012 10:58 PM
    • Marked as answer by w.benamor Tuesday, November 27, 2012 2:30 PM
    Friday, November 2, 2012 12:54 PM
  • Thanks a lot for your help.

    the task must be marked as terminted and exctract/publsh the project after what the task disappear.

    Tuesday, November 27, 2012 2:31 PM