PWA (Resource Center) vs. Project 2007 - % Work Complete Discrepencies RRS feed

  • Question

  • Hello,

    On Project 2007 (12.0.6607.1000) SP3 MSO (12.0.6718.5000)

    I am having an issue where a project will have a task/milestone showing 100% complete in MS Project, but in PWA under Resource Center, the task will show 0%. 

    The resources are manually adjusting their % Complete and % Work Complete to 100% when finished. For my purposes, I am only interested in tracking milestones for 100% completeness.

    Searched online but the only solutions I've seen are for Project 2003.

    Any help would be appreciated.

    Thanks,


    • Edited by BL_ Tuesday, May 19, 2015 3:32 PM typo
    Tuesday, May 19, 2015 3:31 PM

All replies

  • Hi,

    First of all, I'm a bit confused when you say that the task show 0% in the resource center. The resource center shows no tasks but resources.

    Then try to publish again the project and see if it helps.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Wednesday, May 27, 2015 7:51 AM
    Moderator
  • Hi, thanks for the reply.

    To view the status of all tasks under the selected resource in Resource Center, I click View Assignments. 

    We've created a customized view, which includes columns such as Project Name, Task Name, Resource Name, and % Work Complete.

    I can provide more information if needed.

    Thanks again.

    Wednesday, May 27, 2015 1:54 PM
  • Have you tried re publishing the project?

    Is it just occuring for 1 unique project? 

    How do the users enter the % work complete and the % complete?


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Wednesday, May 27, 2015 2:26 PM
    Moderator
  • Yes we've tried republishing all projects with no changes.

    This problem is occurring for multiple projects for multiple resources.

    For entering % complete/work complete, we have a split of users both changing the values in Project, and changing the values through PWA.

    Thanks,

    Wednesday, May 27, 2015 2:29 PM
  • You have to be careful that the % work complete is different at assignment level and task level, see the example below. So if you look at the task % work complete in the project plan and at the assignment % work complete in the resource center, it might be a normal behavior. 

    Task C % work complete is 25% where as the % work complete on resource A assignment is 40%.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Wednesday, May 27, 2015 2:40 PM
    Moderator