View all Assignments RRS feed

  • Question

  • Hi. How do I view everyone's assignments?  How can I close other peoples tasks down (mark them as 100%)  I have full admin access.

    Thank you

    Wednesday, March 7, 2018 10:45 AM

Answers

  • Hello,

    Using PWA you can access the Resource Center and select the Resource/s then click Resource Assignments to see the assignments for the selected resources or you can create a report.

    To mark all tasks 100% complete you would need to go into the project schedules and progress / complete the tasks / assignments.

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS | MVP | Downloads

    Wednesday, March 7, 2018 6:04 PM
    Moderator