  • I'm very new to Project 2010 Standard and am looking for recommendations for the best way to assign a task owner. Specifically, I have a number of tasks where multiple resources are assigned to each task. In my schedule I want to show who the task owner is so it is clear who is responsible for making sure the task is completed. Should I just add a custom field column to show the task owner or is there a better way to do this?
    Friday, June 24, 2011 3:19 PM

Answers

  • domcm --

    I personally would lean toward using a custom task Text field called Task Owner.  If you have a fairly small project team, you could create a Lookup Table in the custom field and list the names of every team member.  Then for any task, after you have assigned resources to the task, you could double-click the task, click the Custom Fields tab, and select a value in the Task Owner field as well.  Alternately, you could also insert the Task Owner column in the Gantt Chart view and select the owner.  Hope this helps.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    • Marked as answer by domcm Tuesday, June 28, 2011 7:26 PM
    Friday, June 24, 2011 3:41 PM
    Moderator