  • Greeting All,

      I have a question, My company is currently using Project Online, and management has decided to change the current workflow being used. In addition, the decision has been made to remove 2 of the workflow phases which previously existed. My question(s) are as follows:

    1. What are the ramifications to those projects that are currently in one of the phases scheduled for removal?
    2. Must I install the new workflow, restart the workflow for those project in a "to be deleted" phase and force those project to a new corresponding phase, and then remove the "to be deleted" phases?

    I am fairly new to Project server / project online so any help would be greatly appreciated

    Thank You

    Monday, March 16, 2015 4:53 PM

All replies

  • 2. Must I install the new workflow, restart the workflow for those project in a "to be deleted" phase and force those project to a new corresponding phase, and then remove the "to be deleted" phases?

    Eugene,

       Sounds like you have a have a pretty good handle on the situation - your number 2 option is precisely what I would do, however the new workflow must be careful to implement the "skip-to-stage" functionality in order to be able to use the "Change or restart workflow" feature.

    Good luck,

       James.


    James Boman BSc. MCP:EAD -
    • Edited by James Boman Wednesday, March 18, 2015 3:12 AM