No announcements
Found 635794 threads
-
0 Votes
Unique ID Task
I'm working with both PWA and Project Pro but what I want is in Project Pro. As you can see, I have an ID task column wich is custom and I want the number unique. I ...Unanswered | 5 Replies | 5122 Views | Created by r.ambroise - Monday, January 23, 2012 2:43 PM | Last reply by r.ambroise - Tuesday, January 24, 2012 8:59 AM -
1 Votes
Move Task and Keep Task Unique ID
I am desperately trying to find this task level Unique ID field in any of the database tables and fields, and I'm not having any luck, can anyone direct me to where I may ...Answered | 3 Replies | 3938 Views | Created by TechNetAndy - Sunday, March 17, 2013 12:56 AM | Last reply by Raymond Wohltman - Monday, February 24, 2014 7:29 PM -
0 Votes
Unique ID of a summary task
How do I find the Unique ID of the summary task header. For Example: Task 1 UID ...Proposed | 1 Replies | 5758 Views | Created by Proware1 - Tuesday, August 2, 2011 11:34 PM | Last reply by John - Project - Wednesday, August 3, 2011 2:52 AM -
0 Votes
Reading Task Field Unique Id through PSI
Hi, You can retrieve the Task Unique ID (GUID) with this call:Answered | 4 Replies | 12207 Views | Created by Adrian Miller - Monday, June 21, 2010 4:09 PM | Last reply by AbhishekJangid - Friday, June 25, 2010 10:02 AM -
0 Votes
Task Level Unique ID field.
There are three ID fields in the MSP_EpmTask_UserView; TaskUID, TaskIndex and TaskClientUniqueId. TaskUID is a GUID, TaskIndex corresponds to the Task ...Answered | 8 Replies | 4061 Views | Created by Raymond Wohltman - Monday, February 24, 2014 6:47 PM | Last reply by AkitoAkito - Thursday, January 23, 2020 7:16 AM -
0 Votes
Unique ID - in master project for sub projects` tasks - & - Task Summary Name in SQL Database table
Hi All, I found the "Task Summary Name" but not yet lucky for "Unique ID" - in master project Answer (for ...Unanswered | 1 Replies | 612 Views | Created by AkitoAkito - Thursday, January 23, 2020 7:04 AM | Last reply by AkitoAkito - Thursday, January 23, 2020 7:48 AM -
0 Votes
UniqueIDSuccessors and the ListSeparator
Developing against MS Project I have a question about two members.Answered | 3 Replies | 981 Views | Created by Jim01 - Thursday, June 8, 2017 4:19 PM | Last reply by Jim01 - Thursday, June 29, 2017 2:40 PM -
0 Votes
Microsoft Project: How Do I Refer to Project Tasks using the Unique ID?
referred to by the Task ID, not the Unique ID. So, am I being forced into a bad solution, or is there a way to do what I want... namely, make the ... -
0 Votes
Task Creating with InfoPath Form
Table with Unique ID and the Task will be created through Workflow for the Approver ( I used Windows Workflow Foundation in VS 2005 to create the ...Unanswered | 1 Replies | 7134 Views | Created by Umesh_K - Monday, September 17, 2007 10:31 AM | Last reply by Paul Galvin - Tuesday, September 18, 2007 12:40 AM -
0 Votes
Ignore Actual Date Unexpectedly in Excel File by Excel Import to Local Project
Data Type : Task (only) Microsoft Excel Option : Include Header Map : (Excel Fields are ...Answered | 1 Replies | 13503 Views | Created by nagino - 引退エンジニア - Thursday, December 10, 2009 3:27 AM | Last reply by Matt Roe - Friday, January 8, 2010 6:25 PM -
0 Votes
Clear Actual Date Unexpectedly in Enterprise Project by Excel Import
) Microsoft Excel Option : Include Header Map : (Excel Fields are default) Unique ...Answered | 1 Replies | 12518 Views | Created by nagino - 引退エンジニア - Thursday, December 10, 2009 3:12 AM | Last reply by Matt Roe - Friday, January 8, 2010 6:26 PM -
0 Votes
getting unique id from project server
Hi, I needed to have Project 2007 Task Unique ID field on PWA.I Created a custom field (number) and associated in formula the Unique Id. ...Unanswered | 1 Replies | 5703 Views | Created by Azra Ansari - Friday, December 18, 2009 4:59 AM | Last reply by Sachin Vashishth - Thursday, December 24, 2009 8:03 AM -
1 Votes
Integration between SAP Recipe Development (RD) and MS Project
you need to match a record in RD with a Task in Project then you need to have the Project Unique ID or Task name in RD. Rod GillUnanswered | 4 Replies | 1596 Views | Created by jkothompson - Friday, November 15, 2013 8:59 PM | Last reply by Bastian Emondts - Friday, December 6, 2013 12:35 PM -
0 Votes
Task List formula issue
Hi I hope someone can help I have a task list in sharepoint which I use to track incoming workload to my team. I added a custom column to issue a ...Answered | 4 Replies | 614 Views | Created by Matt22365 - Monday, August 6, 2018 8:52 AM | Last reply by Matt22365 - Monday, August 6, 2018 1:33 PM -
0 Votes
Using resource loaded data from another product
Yes. Can you create a spreadsheet with task unique id followed by the data you want to import? Opening that spreadsheet will merge the data into your ...Unanswered | 1 Replies | 9045 Views | Created by mdrlwalsh - Tuesday, February 22, 2011 7:33 PM | Last reply by Rod Gill - Monday, February 28, 2011 8:29 AM -
0 Votes
Maintaining Excel - Project Links
This is possible. Be sure to only bring in the items you want, and create the merge key on the task unique ID. Note that the notes field will only update 127 characters. I ...Unanswered | 1 Replies | 2307 Views | Created by AshMarRee - Monday, October 29, 2012 6:02 PM | Last reply by Ben Howard [MVP] - Monday, October 29, 2012 7:36 PM -
0 Votes
Displaying a Custom ID for a Task
I'm creating a task list and need to display a unique ID for each new task. Users will need to be able to copy and paste the ID when displaying a ...Answered | 1 Replies | 4970 Views | Created by Jeff Gutsell - Tuesday, June 14, 2011 1:40 PM | Last reply by Mike Walsh FIN - Tuesday, June 14, 2011 2:01 PM -
0 Votes
issue syncing MS Project list to SharePoint Online task list
displayed in a particular order. Then there is "Unique ID (task field not resource field)" which is the order in which you created the tasks. ... -
0 Votes
SharePoint 2010 Designer Customization Task (Give a unique ID for a Div in each row in a dataview.)
Hi everybody, In order to draw a DIV in the first cell in every row in a dataview I wanted to assign a unique ID for each DIV in a row so I did the ...Answered | 1 Replies | 3948 Views | Created by Gamil Silvergeek - Tuesday, February 28, 2012 11:06 AM | Last reply by Qiao Wei - Thursday, March 1, 2012 6:17 AM -
0 Votes
using unique ID to match tasks with timesheet system
eagle one3, Julie makes an excellent point. There is only one Unique ID per task so if you use a macro to copy that to a custom assignment field in the ...Proposed | 12 Replies | 4317 Views | Created by eagle one3 - Tuesday, November 12, 2013 7:02 PM | Last reply by Martyn Iv - Monday, October 12, 2015 4:43 PM - Items 1 to 20 of 635794 Next ›
No announcements