Expanding summary tasks in master project file (VBA)
In Project 2013 have a master project file with several projects linked as subprojects. I want to import all tasks into an Excel range as ...Answered | 4 Replies | 1486 Views | Created by Huismu5 - Friday, December 18, 2015 1:03 PM | Last reply by John - Project - Friday, January 8, 2016 3:50 PM -
0 Votes
Looping through Summary Tasks in VBA
Thanks Rod - That solution worked. John - I have VBA code that grabs information from an access database and brings it into the project file but I ...Answered | 5 Replies | 1160 Views | Created by pd240 - Thursday, May 18, 2017 12:39 PM | Last reply by John - Project - Friday, May 26, 2017 1:50 AM -
2 Votes
VBA Help with Summary Tasks
I am trying to write VBA to sum children tasks if the summary task is 0. If it is not 0, then do nothing: If(Expression, True, ...Answered | 7 Replies | 10599 Views | Created by cwilkins59 - Friday, April 15, 2011 12:45 PM | Last reply by John - Project - Monday, May 9, 2011 4:08 PM -
0 Votes
VBA Help with Summary Tasks
appropriate charge item (like a job number, etc.) I enter the AC on the "Actual Cost - Acct 1234" line. Since many tasks in the file ...Answered | 10 Replies | 10051 Views | Created by cwilkins59 - Thursday, April 14, 2011 5:21 PM | Last reply by Sapna Shukla, MCTS, Project MVP - Friday, April 15, 2011 12:45 PM -
0 Votes
Summary Tasks in My Work
; So they are not sure for which summary task this is referring. Is it possible to show the related summary tasks, or do I have to put detailed descriptions ...Answered | 3 Replies | 4803 Views | Created by Vassily Zeitsev - Monday, August 6, 2012 9:03 PM | Last reply by Vassily Zeitsev - Tuesday, August 7, 2012 6:42 PM -
0 Votes
Summary tasks in Timeline in manual scheduled project template
summary tasks are updated in the timeline if the dates are changed in a project based to the template.Answered | 3 Replies | 1040 Views | Created by jjy-fin - Monday, July 6, 2015 6:28 PM | Last reply by jjy-fin - Wednesday, July 8, 2015 8:14 PM -
0 Votes
Project Server 2010 - Resource Assignments summary tasks
'Summary Tasks' IS checked. In Project 2007, on the Resource Assignments screen (for a particular ResourceAnswered | 1 Replies | 5263 Views | Created by andythingelse - Thursday, July 12, 2012 3:01 PM | Last reply by Treb Gatte, Data Platform MVP, MBA, MCP, MCTS - Thursday, July 12, 2012 4:20 PM -
0 Votes
How to handle MS Project Summary Tasks
so i cant directly link into TFS, but i have the excel add-in. I have exported the MS Project file into excel and got a list of tasks, but thats been flattened out ...Answered | 2 Replies | 4390 Views | Created by Benjy - Monday, September 3, 2007 5:36 PM | Last reply by Ognjen Bajic - Wednesday, September 12, 2007 4:27 AM -
0 Votes
Summary Tasks / Tasks in a List - MS Project Synchronization
synhronized with the SharePoint Task List, because at least 2 summary tasks have the same name. How to deal with that situation? Is it ...Answered | 1 Replies | 3706 Views | Created by MarcJe - Friday, July 13, 2012 10:16 AM | Last reply by Pengyu Zhao - Monday, July 16, 2012 5:42 AM -
0 Votes
Assigning resources to Requirements as Summary Tasks in Project
Hi - In a normal Microsoft Project file, one organizes tasks in a hierarchy of summary tasks ...Answered | 5 Replies | 6087 Views | Created by nw_LHC - Wednesday, April 25, 2007 6:07 PM | Last reply by Yogita Manghnani - MSFT - Wednesday, May 16, 2007 8:20 PM -
0 Votes
show only summary tasks (project 2010)
Pratrap, You answered your own question on the first one. It you only want to see summary tasks and do not want to use the built-in "Summary ...Answered | 3 Replies | 7348 Views | Created by Pratrap - Friday, August 10, 2012 7:38 PM | Last reply by John - Project - Saturday, August 11, 2012 5:20 PM -
0 Votes
Project Summary and Tasks not showing up in project online
Yes the default view set for the tasks and project summary are empty. There seems to be an error message in the queu Job ...Answered | 12 Replies | 1699 Views | Created by RoopaC - Wednesday, November 14, 2018 10:48 AM | Last reply by RoopaC - Wednesday, November 14, 2018 12:10 PM -
0 Votes
Work Items and MS Project Summary Tasks
This seems to be half working in that if I create a new MS Project file, import all work items in, modify the hierarchy (i.e indent tasks) and then publish ...Answered | 2 Replies | 4729 Views | Created by Rob Biernat - Wednesday, October 19, 2005 8:26 AM | Last reply by Smitha Saligrama- MSFT - Wednesday, October 19, 2005 4:15 PM -
0 Votes
Rollup Tasks formatting in Summary tasks
Hi, In MS Project 2007, i have number of summary tasks with the subtasks. Sub tasks are in different colors, ...Answered | 7 Replies | 12071 Views | Created by K.Gokulraj - Tuesday, November 22, 2011 7:42 AM | Last reply by John - Project - Monday, August 22, 2016 2:58 PM -
0 Votes
Master Project - Rearranging Subproject tasks into Phases
table for "phase". 2) Populate this field, with the correct Phase names, for each of the tasks in the Sub projects 3) In the ...Answered | 1 Replies | 681 Views | Created by VisionaryRose - Thursday, April 14, 2016 3:02 PM | Last reply by Prasanna Adavi - Thursday, April 14, 2016 3:38 PM -
0 Votes
Master Project external tasks in OData
I have a master project having multiple sub projects inserted, I am trying to build a report from oData, Is there a way to get these external tasks in Odata feed ...Answered | 2 Replies | 667 Views | Created by PSI Developer - Tuesday, May 3, 2016 3:59 PM | Last reply by PSI Developer - Wednesday, May 4, 2016 7:37 PM -
1 Votes
Gantt Chart, Summary Tasks
I have a huge problem with the Gantt Chart view for the project tasks, problem is that when I create a summary task in my .mpp and synchronize with the SharePoint ...Answered | 4 Replies | 15008 Views | Created by John Foot - Thursday, April 28, 2011 9:31 AM | Last reply by achenchk - Wednesday, July 17, 2013 6:25 AM -
0 Votes
Summary Task Expansion in Master Projects
. It is more of an annoyance than a real problem, but I am losing a lot of time to closing and expanding the lists repeatedly. Basically, is there a way to keep my ...Answered | 3 Replies | 779 Views | Created by Root.root - Thursday, June 5, 2014 4:25 PM | Last reply by John - Project - Thursday, June 5, 2014 8:11 PM -
0 Votes
Task in subproject as sub tasks in master project?
adds up entire IT Project duration to this Summary tasks. Master Project or Consolidated projects are used to show Program Level ...Answered | 6 Replies | 9781 Views | Created by dominikj - Friday, February 25, 2011 4:08 PM | Last reply by Sapna Shukla, MCTS, Project MVP - Saturday, February 26, 2011 3:36 PM -
0 Votes
Resource assignments to summary tasks not visible in Project Online
Karen, Did you check the box that says "Summary Tasks" ? Also, the summary task will appear as an assignment in the list. See the ...Answered | 2 Replies | 810 Views | Created by KarenStephansen - Tuesday, November 1, 2016 4:28 PM | Last reply by KarenStephansen - Tuesday, November 1, 2016 6:22 PM - Items 1 to 20 of 2723007 Next ›