0 Votes
Displaying milestone sub-task symbol inside Project Summary Bar
, but I would like to display the milestones for the respective milestone sub-tasks in my project summary bar. Is there a way to do this in ...Unanswered | 2 Replies | 1021 Views | Created by mgd2014 - Wednesday, April 13, 2016 8:56 PM | Last reply by Julie Sheets - Thursday, April 14, 2016 12:37 PM -
1 Votes
Milestone Summary Bar
Hi, If it doesn't mess up the schedule, I would give the milestones a non-zero duration and in Task Information, Advanced, check "Mark Task as ...Answered | 3 Replies | 8678 Views | Created by Cadilly - Tuesday, November 2, 2010 8:55 AM | Last reply by Jan De Messemaeker - Project MVP - Tuesday, November 2, 2010 12:37 PM -
0 Votes
Milestone Bar Symbol size
No you can't. You can just increase the task name font size. An alternative is to insert a drawing attached to the task, setting the size you need.Answered | 1 Replies | 889 Views | Created by Stev Scott42 - Monday, October 6, 2014 10:44 AM | Last reply by Guillaume Rouyre [MBA, MVP, MCC] - Monday, October 6, 2014 11:27 AM -
0 Votes
Summary View with Milestone Markers
Hello, Is it possible to create a summary view in Project that also includes milestone markers along the timeline? Would look something ...Answered | 5 Replies | 637 Views | Created by Will Kelly - Tuesday, February 14, 2017 3:54 PM | Last reply by John - Project - Tuesday, February 14, 2017 6:18 PM -
1 Votes
Show Project Summary bar
You can also get to it in File - Options - Advanced - Show Project Summary TaskAnswered | 4 Replies | 11938 Views | Created by Sleekstone - Thursday, February 25, 2010 12:03 PM | Last reply by Sleekstone - Thursday, February 25, 2010 5:09 PM -
0 Votes
Task Milestone
Hi Hasan, By default, if you set the duration to 0, the "is milestone" field will be set to Yes (task #1 in the screenshot below). You ...Answered | 1 Replies | 676 Views | Created by Hasan Jamal Siddiqui - Wednesday, October 5, 2016 8:05 AM | Last reply by Guillaume Rouyre [MBA, MVP, MCC] - Wednesday, October 5, 2016 9:13 AM -
1 Votes
CSOM Project Summary Task
blogged a nice technical discussion that confirms what you posted back in 2014: the Project Summary Task is being filtered out of the CSOM PublishedTask ...Answered | 3 Replies | 2689 Views | Created by Mike Hardy - Saturday, December 6, 2014 1:09 AM | Last reply by Mike Hardy - Thursday, May 26, 2016 12:43 AM -
2 Votes
Project summary task
summary task as well) is linked to each sub-project's source file. Thanks Again! Gregg D. Richie, PMP, MCTS; Author, Microsoft ...Answered | 10 Replies | 12813 Views | Created by Mimi Laongpanich - Monday, October 24, 2011 2:56 PM | Last reply by DeanLC - Wednesday, October 26, 2011 7:01 PM -
0 Votes
Bug with milestone task.
what Im really suggesting is that while Project allows you to mark a non-zero duration task with work assigned to a resource as a milestone that this task is not ...Proposed | 11 Replies | 8158 Views | Created by Chernobrivec - Friday, January 20, 2012 12:43 PM | Last reply by Chernobrivec - Tuesday, January 24, 2012 1:52 PM -
0 Votes
Project Site not showing task as milestone
as a bar that spans those dates. If a task has only a due date or a start date, it appears as a single point on the timeline, marked with a ...Answered | 2 Replies | 2568 Views | Created by Carlos GC - Tuesday, March 4, 2014 5:56 PM | Last reply by Carlos GC - Thursday, March 6, 2014 3:07 PM -
0 Votes
display current task name on summary task gant bar
Hello , I am looking at a summary task view gant bar. The summary task has many detailed tasks under it. is there a ...Unanswered | 1 Replies | 755 Views | Created by eahamdan - Monday, February 15, 2016 4:25 PM | Last reply by John - Project - Monday, February 15, 2016 5:04 PM -
0 Votes
Project Summary Task - Plan Template
ASQU -- I have discovered that if I create a new project using an EPT in Project Web App, the Project Summary Task (Row 0 or ...Answered | 5 Replies | 1546 Views | Created by ASQU - Thursday, June 28, 2018 2:18 PM | Last reply by ASQU - Monday, July 2, 2018 6:46 AM -
0 Votes
MS Project Milestone
In MS Project, I used to create milestone. If I create/publish a milestone in MS Project, what will happen to the TFS workitem? ...Answered | 1 Replies | 3996 Views | Created by jason Luo - Wednesday, May 26, 2010 6:38 PM | Last reply by Cathy Kong - Thursday, May 27, 2010 7:37 AM -
0 Votes
How to insert sub-projects milestones to master project milestone?
milestone implementation. All sub projects (features) have same milestone start date and finish date. 3. So now comes the ...Answered | 3 Replies | 11528 Views | Created by RachelMich - Wednesday, February 16, 2011 5:08 AM | Last reply by Ben Howard [MVP] - Wednesday, February 16, 2011 7:02 PM -
0 Votes
How can I set the summary task name of a sub-task in the main project
Does anyone knows how can I set the sub-project name in the main project. when I add sub-project to my main project the ...Proposed | 3 Replies | 4503 Views | Created by Shaniky12 - Wednesday, August 29, 2012 9:40 AM | Last reply by Andrew Simpson - Thursday, August 30, 2012 8:22 AM -
0 Votes
Task became a milestone
Using Project Server 2010 with SP1 - I have encountered some cases where completed tasks with duration and work greater that zero have suddenly changed: the task became a ...Unanswered | 2 Replies | 5654 Views | Created by Yoavs - Thursday, December 1, 2011 9:45 AM | Last reply by PWMather - Thursday, December 1, 2011 3:18 PM -
0 Votes
Master Project Group by Summary and Task
I am using MS Project 2010 Standard and have a master project with 10-15 sub-projects. I know how to sort by task but I would like to sort by summary ...Unanswered | 2 Replies | 2610 Views | Created by cassyanmeljer - Monday, February 4, 2013 2:00 AM | Last reply by John - Project - Monday, February 4, 2013 4:10 PM -
0 Votes
Project 2010 - Error message when creating new milestone bar styles
Hi There, I'm trying to create a new milestone bar style in project 2010 so that I can set the colour based on whether the activity is classed as 'Marked' ...Answered | 4 Replies | 1223 Views | Created by Murray G A - Wednesday, August 13, 2014 3:41 AM | Last reply by John - Project - Monday, August 18, 2014 4:14 PM -
0 Votes
Task is Milestone
May not the latest patch of Project Pro 2013 installed on all users. Have no clue on pattern when it occurs, its behaving randomly, majority times works properly with ...Unanswered | 6 Replies | 881 Views | Created by NomanSohail - Thursday, June 9, 2016 7:46 AM | Last reply by PWMather - Monday, June 13, 2016 10:05 AM -
0 Votes
Using Milestone summary report for status to Stakeholders
tasks that roll to a milestone task or do I need to just have my milestones and then take the percent complete from say the main summary tasks for each ...Unanswered | 1 Replies | 1159 Views | Created by Portfoliodude - Sunday, December 8, 2013 5:10 AM | Last reply by Allen Li - MSFT - Tuesday, December 10, 2013 5:44 AM - Items 1 to 20 of 1026458 Next ›