Change Working Time - For Calendar
When trying to build a 24 hour schedule with (2) 12 hour shifts, I was able to go into the "Project" tab and "Change Working Time" button, ...Unanswered | 1 Replies | 725 Views | Created by cpr2013 - Wednesday, March 15, 2017 9:03 PM | Last reply by John - Project - Wednesday, March 15, 2017 9:50 PM -
0 Votes
Change working time for a resource calendar
I have a project using its own resources. 2 of the resources will work a half day every 3rd Friday. I tried to set this up in Change Working Time as ...Unanswered | 6 Replies | 2813 Views | Created by MBradford7613 - Thursday, January 24, 2013 3:55 PM | Last reply by MBradford7613 - Friday, January 25, 2013 2:31 PM -
0 Votes
MSP2007 Change Working Time, "reverse calendar" for April 2011
This is a trivial but annoying problem. Say, in MSP2007, I want to create a "reverse calendar" for April 2011. I want all of the week days to be non-working days, ...Answered | 1 Replies | 8070 Views | Created by Trevor Rabey - Thursday, April 21, 2011 2:28 AM | Last reply by Jan De Messemaeker - Project MVP - Thursday, April 21, 2011 8:05 AM -
0 Votes
Code for Outlook to change working hours
like to change start and end of my working time per macro in order to write a code around this for viewing the calender only in specifc timeframes - e.g. ... -
1 Votes
How do I set a 4 day work week 10 hrs a day?
nonworking time.Close all dialogs. Tools - Options - tab Calendar. Change Default start time, Default end time hours per day and days per moth ...Answered | 1 Replies | 7715 Views | Created by Billbostwick - Friday, October 28, 2011 4:15 PM | Last reply by Barbara Henhapl - Friday, October 28, 2011 5:00 PM -
1 Votes
Change Working Time within embedded projects
continuing to work over the break. How do I change the working time for 1 project with the programme? I have tried opening theAnswered | 1 Replies | 4408 Views | Created by ah666 - Wednesday, November 30, 2011 3:57 PM | Last reply by John - Project - Wednesday, November 30, 2011 5:07 PM -
1 Votes
Ent.Calendars for Project Server Resources
Change the working time for the resource calendarSave and check-in the resource Check if this makes a difference or try to change the ...Proposed | 2 Replies | 2568 Views | Created by Paul Conroy - Monday, February 4, 2013 6:22 PM | Last reply by HFprojects - Sunday, September 29, 2013 12:07 PM -
0 Votes
MSP 2010 manually scheduled tasks
clicking on Calculate project. For a specific task if I change the calendar from 5 days working to 6 days working, bar changes as per the new ...Answered | 3 Replies | 8647 Views | Created by vanita ahuja - Wednesday, December 22, 2010 8:23 AM | Last reply by vanita ahuja - Thursday, December 23, 2010 8:11 AM -
0 Votes
Best practices for changing resource's calendars
resource's calendar using the button Change Working Time and save changesWe add the new working week for the resource, stating the beginning -
0 Votes
Project stops working when attempting to change working times
operation, it now appears that Project has deleted (or corrupted) one of the base calendars that several of the resources use. Now, when attempting to change working ...Unanswered | 2 Replies | 699 Views | Created by Jim925 - Friday, January 30, 2015 2:04 AM | Last reply by Sai Prasad, PMP, PMI-SP, MCTS, MVP - Friday, January 30, 2015 3:29 AM -
0 Votes
Duration not adding up
is done in 10days. I suggest to create a new calendar based on Standard and set weekends to working days: Project - Change ...Unanswered | 1 Replies | 486 Views | Created by Kate41195 - Thursday, March 9, 2017 12:04 PM | Last reply by Barbara Henhapl - Thursday, March 9, 2017 12:27 PM -
0 Votes
Changing Working Time Project Professional 2010
Resource Pool. Double-click the name of the resource and then click the Change Working time button. You should now be able to change the ...Answered | 1 Replies | 5590 Views | Created by Craig_Smillie - Wednesday, August 17, 2011 3:40 PM | Last reply by Dale Howard [MVP] - Thursday, August 18, 2011 3:33 AM -
1 Votes
How do I use a local base calendar in Project 2010
project. I've tried using a local base calendar by opening the project in Project Pro 2010, going to the Project tab | Change Working Time | ...Answered | 2 Replies | 5806 Views | Created by Bill Ellsworth - Friday, November 11, 2011 8:05 PM | Last reply by Dale Howard [MVP] - Saturday, November 12, 2011 4:42 PM -
0 Votes
change working time with project professional 2010
doing: I open a existing project I click on "Change Working Time" and select from "For calendar" the ...Answered | 5 Replies | 12084 Views | Created by samantha.tedesco - Thursday, September 23, 2010 1:49 PM | Last reply by Dale Howard [MVP] - Friday, September 24, 2010 12:27 PM -
0 Votes
Project Server 2010 Calendar Upload
.On the 'Enterprise Calendars' page, click the 'New Calendar' toolbar button.In the 'Change Working Time' dialog box that opens in Project Professional, enter a ...Unanswered | 1 Replies | 2244 Views | Created by en1701d - Thursday, September 19, 2013 5:06 PM | Last reply by t0nyz1nk - Thursday, September 19, 2013 11:01 PM -
1 Votes
Shared Calendar Capabilities
I am currently working on a team calendar for our after business hours on-call rotation. The hours for this service are from 5:01PM CT Mon - Fri and 24 hours on ...Proposed | 1 Replies | 288 Views | Created by HCASRTECK - Thursday, December 7, 2017 3:16 PM | Last reply by Dennis Guo - Friday, December 8, 2017 9:22 AM -
0 Votes
make sunday as working day
days and times that you entered for the other calendar. To synchronize multiple calendars to a resource's base calendar (which you created in the Change ...Answered | 1 Replies | 10021 Views | Created by rchokler - Friday, May 9, 2008 2:36 PM | Last reply by John T Nierenberg - Friday, May 9, 2008 3:35 PM -
1 Votes
How to set a calendar and time properly
at 20:00. I have changed the timing and hours in the 'SCHEDULE' tab as well as creating a new calendar through the 'Change Working Time' tab. But each ...Unanswered | 1 Replies | 561 Views | Created by Muneeb-Ahmad - Monday, May 23, 2016 2:55 PM | Last reply by Ben Howard [MVP] - Monday, May 23, 2016 6:23 PM -
0 Votes
Microsoft Project Change working hour
Hi, You need to change two settings. One, Tools, Change Working time, Work weeks, select all working days and ...Answered | 2 Replies | 13615 Views | Created by Foong Kim - Wednesday, June 30, 2010 9:06 AM | Last reply by MikeGlen - Wednesday, June 30, 2010 1:43 PM -
0 Votes
Create a range of non-working days
the Change Working Time window, select the two days as shown. Then create the exception. When you clickUnanswered | 3 Replies | 710 Views | Created by Brad Birdsong - Tuesday, January 3, 2017 4:57 PM | Last reply by John - Project - Tuesday, January 3, 2017 8:09 PM - Items 1 to 20 of 2588362 Next ›