    I am trying to create a Custom field that checks if the Baseline Start or Baseline Finish fields exist.Please help.

    Wednesday, March 8, 2017 3:05 AM

All replies

  • Hi,

    here a sample for Baseline Start.

    IIf(projdatevalue([Baseline Start])=4294967295,"No Baseline Start","Baseline Start")

    I'am using "4294967295" for date validation, since this value is language independent.

    Does that help?
    Barbara


    To increase the value of this forum, please mark the replies that helped to solve your issue as answer. If you find answers to questions from other forum participants to be helpful, please mark them as helpful. Your participation will help others to find an appropriate solution faster. Thanks for your support!