Resource engagement percentage RRS feed

  • Question

  • I was wondering if someone can advise me how I can get percentage of engagement of resource per month and their free time considering the max hours per day and Planned assignments.

    Regards, Syed Faizan ur Rehman, CBPM®,PRINCE2®, MCTS

    Tuesday, September 2, 2014 6:18 AM

Answers

  • Developed a report using Excel services with formula for a column.

    Regards, Syed Faizan ur Rehman, CBPM®,PRINCE2®, MCTS

    Sunday, September 28, 2014 6:02 AM

All replies

  • Use the Resource Usage view zoomed out to show months.  Add the Percent Allocation field to the timescaled portion (right side) of the view to view percent of max units in use in assignments.  You may also find the remaining availability field is helpful.
    Tuesday, September 2, 2014 12:33 PM
    Moderator
  • Developed a report using Excel services with formula for a column.

    Regards, Syed Faizan ur Rehman, CBPM®,PRINCE2®, MCTS

    Sunday, September 28, 2014 6:02 AM