none
How to create split task using PSI (Project Server 2013)? RRS feed

  • Question

  • Is there any way to split a task using PSI in Project Server 2013?

    for example: i want to create a task that have time in Tuesday 8h, Wednesday 0h, Thursday 0h and Friday 8h.

    is that possible to do that using PSI? because i can do that using project professional

    Thanks,

    Anjar


    • Edited by Anjar Priantoro Monday, February 16, 2015 3:49 AM add detail version
    Monday, February 16, 2015 3:45 AM

Answers

All replies

  • Hi,

    As far as I know, there is no way to do that. Please refer to this similar thread.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Monday, February 16, 2015 1:45 PM
    Moderator
  • Hi Guillaume Rouyre,

    Thank you for your info, i've read that post before. i just thought that maybe in newer version of project server. Microsoft have give some changes in PSI and support that thing.

    Tuesday, February 17, 2015 1:25 AM
  • Not to my knowledge, it is still the same.

    Please mark any reply as an answer if it was helpful to you.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Tuesday, February 17, 2015 6:55 AM
    Moderator