none
overview of work per person for a specific period of time RRS feed

  • Question

  • Hi all,

    I am wondering how I can get a good overview of all the tasks and hours per person for a specific period of time.
    Let's say I have a project from januari till december with multiple tasks and assigned work but I only want to view the hours of work and which tasks these are assigned to for april - may. How can I do this?

    Thanks
    Thursday, February 21, 2019 3:29 PM

All replies

  • Hi,

    Use either the resource usage or the task usage view, and select the timescale to weeks or months and adjust the right hand window so you are just seeing April & May. Additionally, you could select the 2date range" filter once you have applied the view.


    Ben Howard [MVP] | web | blog | book | downloads | P2O

    Thursday, February 21, 2019 3:37 PM
    Moderator
  • Thanks that was exactely what is was looking for! 
    Friday, February 22, 2019 9:41 AM