Inactivating Tasks via PSI doesn't work for all plans RRS feed

  • Question

  • Project Server 2010 - SP1

    So, I am aware of the limitation around updating only one task at a time if you are going to update the TASK_IS_ACTIVE flag through the PSI.  I have been successfully updating tasks to be inactive in one of my test plans, but when I try to update a task in a copy of a live project plan, it will not update any of the tasks to inactive.  Additionally, it does not return an error.  I know that the QueueUpdateProject service call is working because I can change other content, like dates, but it will not change the TASK_IS_ACTIVE flag.

    Can anyone explain the inconsistent behavior?