    I am creating an approval workflow to SharePoint 2013 and Visual Studio 2013, but i don't now how to use the "composite task" activity in the "completion" section , for example.

    Completion Section.

    CompletedStatus = "Approved"

    CompletionCriteria = "Wait for Percentage.."

    CompletionCriteriaProperties = ?????? (Help me here please).

    Tuesday, April 18, 2017 11:22 AM

Answers

  • I solved it.

    I used BuildDictionary<String,Object> Activity & pass the values as follows-

    Key (String)                  Value (Object)

    Percentage                     75

    InterestedOutcome        3

    And passed this BuildDictionary to CompletionCriteria in Composite Task activity.

    Note:

    - Key should not be in quotes

    - you can use variable instead of 75 and convert that variable to Int32. Don't use % sign.

    Tuesday, April 18, 2017 11:39 AM

All replies

  • I solved it.

    I used BuildDictionary<String,Object> Activity & pass the values as follows-

    Key (String)                  Value (Object)

    Percentage                     75

    InterestedOutcome        3

    And passed this BuildDictionary to CompletionCriteria in Composite Task activity.

    Note:

    - Key should not be in quotes

    - you can use variable instead of 75 and convert that variable to Int32. Don't use % sign.

    Tuesday, April 18, 2017 11:39 AM
  • Hi,

    Glad to hear that you solve this issue, thanks for your sharing, it will help others who suck with the problem!

    Best Regards,

    Dennis


    Please remember to mark the replies as answers if they help.