  • Question

  • How do I get my top line project start and finish date to change? Right now it is showing a date a year and a half after the last date I have for my project completing in a sub task.
    Monday, June 20, 2016 10:29 PM

All replies

  • Chrystal5,

    First of all, what version of Project are you using? Second, is it updated with the latest Cumulative Update? The easiest way to do that is by running Windows Update.

    When you say "top line" may I assume you mean the Project Summary Task? If not, what are you referring to?

    Do you have calculation set for auto (File/Options/Schedule group)?

    Are your tasks auto-scheduled or manually scheduled?

    Are you absolutely sure you have no rogue milestones or tasks that would drive the strange date (sort by Unique ID and look at the last task)?

    A screen shot could be helpful if you can post one.

    John

    Tuesday, June 21, 2016 12:28 AM