Critical Path in the Project Professional 2010 RRS feed

  • Question

  • Hello there.

    How can I show only the tasks that are included in the Critical Path? I would like to see the right side graphical presentation only from that activities too.

    Thanks in advance.


    []'s Juliano Bassetto - [MCT/MCP/MCITP/MCTS] - Semper Fi! Carry On!
    Monday, November 22, 2010 5:54 PM

Answers

  • Expose the field called "Critical" and filter on Critical = Yes....
     
     

    Andrew Lavinsky [MVP] Twitter: @alavinsky Blog: http://blogs.catapultsystems.com/epm
    Monday, November 22, 2010 5:58 PM
  • Hi,

    Besides the option that Andrew has given you; under 'Project' in the menu bar, there is a predefined filteer called 'critical'.  That does the same without needing to open up the field 'critical'.

    Hope this hleps further.

     

    DavidC


    Regards DavidC
    Monday, November 22, 2010 11:14 PM
  • Add a filter to hide summary tasks.
    Jack Dahlgren blogs at:
    Project and Retrovention
    and rarely Twitter
    Tuesday, November 23, 2010 6:11 PM
  • Hi,

    Format ribbon, right edge there is a button alloxwing to hide the summary tasks.

    Tuesday, November 23, 2010 6:21 PM

All replies

  • Expose the field called "Critical" and filter on Critical = Yes....
     
     

    Andrew Lavinsky [MVP] Twitter: @alavinsky Blog: http://blogs.catapultsystems.com/epm
    Monday, November 22, 2010 5:58 PM
  • Hi,

    Besides the option that Andrew has given you; under 'Project' in the menu bar, there is a predefined filteer called 'critical'.  That does the same without needing to open up the field 'critical'.

    Hope this hleps further.

     

    DavidC


    Regards DavidC
    Monday, November 22, 2010 11:14 PM
  • Well, if you want to do it the easy way...sure.  :-)
    Andrew Lavinsky [MVP] Twitter: @alavinsky Blog: http://blogs.catapultsystems.com/epm
    Tuesday, November 23, 2010 12:17 AM
  • Also, critical tasks can be assigned a unique style, if you want to distinguish them.

    Tuesday, November 23, 2010 4:02 PM
  • All right. Understood.

    One last question: in the right area, after selecting only the critical task, how do I hide the tasks that are not tasks? I would like to hide the lines that group tasks, just like we do when we define a project step. That line is only there to group related tasks.

    Thanks in advance again!


    []'s Juliano Bassetto - [MCT/MCP/MCITP/MCTS] - Semper Fi! Carry On!
    Tuesday, November 23, 2010 4:47 PM
  • Add a filter to hide summary tasks.
    Jack Dahlgren blogs at:
    Project and Retrovention
    and rarely Twitter
    Tuesday, November 23, 2010 6:11 PM
  • Hi,

    Format ribbon, right edge there is a button alloxwing to hide the summary tasks.

    Tuesday, November 23, 2010 6:21 PM