Answered by:
Critical Path in the Project Professional 2010

Question
-
Hello there.
How can I show only the tasks that are included in the Critical Path? I would like to see the right side graphical presentation only from that activities too.
Thanks in advance.
[]'s Juliano Bassetto - [MCT/MCP/MCITP/MCTS] - Semper Fi! Carry On!Monday, November 22, 2010 5:54 PM
Answers
-
- Marked as answer by Jack Dahlgren MVP Tuesday, November 23, 2010 6:11 PM
Monday, November 22, 2010 5:58 PM -
Hi,
Besides the option that Andrew has given you; under 'Project' in the menu bar, there is a predefined filteer called 'critical'. That does the same without needing to open up the field 'critical'.
Hope this hleps further.
DavidC
Regards DavidC- Proposed as answer by Fabian Bernal Tuesday, November 23, 2010 7:50 AM
- Marked as answer by Jack Dahlgren MVP Tuesday, November 23, 2010 6:11 PM
Monday, November 22, 2010 11:14 PM -
Add a filter to hide summary tasks.
Jack Dahlgren blogs at:
Project and Retrovention
and rarely Twitter- Proposed as answer by Jack Dahlgren MVP Tuesday, November 23, 2010 6:11 PM
- Marked as answer by Jan De Messemaeker - Project MVP Friday, November 26, 2010 7:23 AM
Tuesday, November 23, 2010 6:11 PM -
Hi,
Format ribbon, right edge there is a button alloxwing to hide the summary tasks.
- Marked as answer by Jan De Messemaeker - Project MVP Friday, November 26, 2010 7:23 AM
Tuesday, November 23, 2010 6:21 PM
All replies
-
- Marked as answer by Jack Dahlgren MVP Tuesday, November 23, 2010 6:11 PM
Monday, November 22, 2010 5:58 PM -
Hi,
Besides the option that Andrew has given you; under 'Project' in the menu bar, there is a predefined filteer called 'critical'. That does the same without needing to open up the field 'critical'.
Hope this hleps further.
DavidC
Regards DavidC- Proposed as answer by Fabian Bernal Tuesday, November 23, 2010 7:50 AM
- Marked as answer by Jack Dahlgren MVP Tuesday, November 23, 2010 6:11 PM
Monday, November 22, 2010 11:14 PM -
Well, if you want to do it the easy way...sure. :-)
Andrew Lavinsky [MVP] Twitter: @alavinsky Blog: http://blogs.catapultsystems.com/epmTuesday, November 23, 2010 12:17 AM -
Also, critical tasks can be assigned a unique style, if you want to distinguish them.
Tuesday, November 23, 2010 4:02 PM -
All right. Understood.
One last question: in the right area, after selecting only the critical task, how do I hide the tasks that are not tasks? I would like to hide the lines that group tasks, just like we do when we define a project step. That line is only there to group related tasks.
Thanks in advance again!
[]'s Juliano Bassetto - [MCT/MCP/MCITP/MCTS] - Semper Fi! Carry On!Tuesday, November 23, 2010 4:47 PM -
Add a filter to hide summary tasks.
Jack Dahlgren blogs at:
Project and Retrovention
and rarely Twitter- Proposed as answer by Jack Dahlgren MVP Tuesday, November 23, 2010 6:11 PM
- Marked as answer by Jan De Messemaeker - Project MVP Friday, November 26, 2010 7:23 AM
Tuesday, November 23, 2010 6:11 PM -
Hi,
Format ribbon, right edge there is a button alloxwing to hide the summary tasks.
- Marked as answer by Jan De Messemaeker - Project MVP Friday, November 26, 2010 7:23 AM
Tuesday, November 23, 2010 6:21 PM