Replacing a resource using PSI RRS feed

  • Question

  • Hi,

    As per msdn documentation, I can see 'ProjectResourcesReplace' is a part of voidQueueUpdateProjectTeam Function.

    This function can be used to update project build team. But I am unable to understand how it can be used to replace resources in build team?

    Can anyone please help here? Thanks.

    Best Regards,

    Anuja

    Wednesday, February 18, 2015 5:55 AM

All replies

  • Looks like PSI do not support below mentioned!!-

    • - Changing the resource on an assignment. However, you can use the PSI to delete the assignment and create a new one.
    • - Requesting or performing resource leveling.
    • - Deleting or replacing a resource that has actual work accepted (actuals).
    Monday, February 23, 2015 9:55 AM
  • Indeed Anujaa, you can refer to this article to see that the PSI cannot replace a resource that has actual. That being said I don't know if you can replace a resource with no actual.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Monday, February 23, 2015 10:17 AM
    Moderator
  • Hi Guillaume,

    I tried that as well, but no luck. I might be doing something incorrectly though :) As I am new to this..

    Thanks for your reply.

    Monday, February 23, 2015 11:49 AM