PSI - Statusing Web Service - Update results not as expected RRS feed

  • Question

  • Hello!

    I'm trying to update Status information on assignments via Statusing Web Service (PSI). Problem is, that the results are not as expected. I'll try to explain what I'm doing in detail:

    Two cases:

    1) An assignment for the resource exists on specified tasks. I want to report work actuals (update status).

    2) There is no assignment for the resource on specified tasks. I want to create the assignment and report work actuals.

    I have one task in my project (Auto scheduled, Fixed work). Resource availability of all resources is set to 100%. They all have the same calendar.

    Task Name Duration Start Finish Predecessors Resource Names Work
    Task 31 - Fixed Work 12,5 days? Thu 14.03.13 Tue 02.04.13 Resource 1 100 hrs


    In case one I execute an UpdateStatus with the following ChangeXML

    <Changes xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xmlns:xsd="http://www.w3.org/2001/XMLSchema">
    <Proj ID="a8a601ce-f3ab-4c01-97ce-fecdad2359d9">
    <Assn ID="d7273a28-c038-486b-b997-cdb2450ceef5" ResID="8a164257-7960-4b76-9506-ccd0efabdb72">
    <Change PID="251658250">900000</Change>
    </Assn>
    </Proj>
    </Changes>

    Then I call a SubmitStatusForResource

    client.SubmitStatusForResource(new Guid("8a164257-7960-4b76-9506-ccd0efabdb72"), null, "auto submit PSIStatusingGateway");

    The following entry pops up in approval center (which looks alright at this point):

    Approval Type -  Name    - Update Type - Resource    - Send Date - Total - % Complete - Remaining
    Status Update -  Task 31 - Task update  - Resource 1 - 3/20/2012 - 15h  - 15%            - 85h

    Update in Project (still looks fine):

    Task Name Duration Start Finish Predecessors Resource Names Work Actual Work Remaining Work
    Task 31 - Fixed Work 12,5 days? Thu 14.03.13 Tue 02.04.13 Resource 1 100 hrs 15 hrs 85 hrs

    Then second case is executed:
    First I create a new assignment...

    client.CreateNewAssignmentWithWork(
                                sName: Task 31 - Fixed Work,
                                projGuid: "a8a601ce-f3ab-4c01-97ce-fecdad2359d9",
                                taskGuid: "024d7b61-858b-40bb-ade3-009d7d821b3f",
                                assnGuid: "e3451938-36a5-4df3-87b1-0eb4b25a1dab",
                                sumTaskGuid: Guid.Empty,
                                dtStart: 14.03.2013 08:00:00,
                                dtFinish: 02.04.2013 15:36:00,
                                actWork: 900000,
                                fMilestone: false,
                                fAddToTimesheet: false,
                                fSubmit: false,
                                sComment: "auto commit...");

    Then I call the UpdateStatus again:

    <Changes xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xmlns:xsd="http://www.w3.org/2001/XMLSchema">
    <Proj ID="a8a601ce-f3ab-4c01-97ce-fecdad2359d9">
    <Assn ID="e3451938-36a5-4df3-87b1-0eb4b25a1dab" ResID="c59ad8e2-7533-47bd-baa5-f5b03c3c43d6">
    <Change PID="251658250">900000</Change>
    </Assn>
    </Proj>
    </Changes>

    And finally the SubmitStatusForResource again

    client.SubmitStatusForResource(new Guid("c59ad8e2-7533-47bd-baa5-f5b03c3c43d6"), null, "auto submit PSIStatusingGateway");

    This creates the following entry in approval center:
    Status Update; Task 31 - Fixed Work; New reassignment request; Resource 2; 3/20/2012; 15h; 100%; 0h

    I accept it and update my project:

    Task Name Duration Start Finish Predecessors Resource Names Work Actual Work Remaining Work
    Task 31 - Fixed Work 6,76 days? Thu 14.03.13 Mon 25.03.13 Resource 1;Resource 2 69,05 hrs 30 hrs 39,05 hrs


    Task Usage:

    Task Name Work Start Finish Actual Work Work Remaining Work
    Task 31 - Fixed Work 69,05 hrs Thu 14.03.13 Mon 25.03.13 30 hrs 69,05 hrs 39,05 hrs
       Resource 2 15 hrs Thu 14.03.13 Fri 15.03.13 15 hrs 15 hrs 0 hrs
       Resource 1 54,05 hrs Thu 14.03.13 Mon 25.03.13 15 hrs 54,05 hrs 39,05 hrs

    And I really don't get, why the new work would be 69,05 hours. I'd like to know how I must set my values when updating status to get results that I expect:

    Task Name Work Start Finish Actual Work Work Remaining Work
    Task 31 - Fixed Work 69,05 hrs Thu 14.03.13 Mon 25.03.13 30 hrs 65 hrs 35 hrs
       Resource 2 15 hrs Thu 14.03.13 Fri 15.03.13 15 hrs 15 hrs 0 hrs
       Resource 1 54,05 hrs Thu 14.03.13 Mon 25.03.13 15 hrs 50 hrs 35 hrs

    I really would appreciate some help. This makes me want to rip my hair out!

    Thanks in advance

    Brigitte

    PS: Forgot to say that I'm working with MS Project Server 2010 and MS Project Professional 2010


    Tuesday, March 20, 2012 3:25 PM

All replies

  • Hm... seems that could narrow down this odd (at least for me) behaviour a bit... it looks like it has something to do with the order I approve the updates. I'll post again, when I confirmed my suspicions.
    Wednesday, March 21, 2012 12:52 PM