none
how to get task approval information using REST in Project Server 2016 RRS feed

  • Question

  • hi all,

    how to get task approval information using REST in Project Server 2016? i can not find any approval informaion in rest api, thanks.

    BR.

    Fanghao


    peardong

    Thursday, July 20, 2017 5:08 AM

All replies

  • Hi,

    within the table "TimesheetLines" you may find "TimesheetLineStatus", which displays the status of each timesheet line. More information here: https://msdn.microsoft.com/en-us/library/office/jj163012.aspx

    Maybe a granularity on a timesheet level is enough for you? If so, use the "Timesheets" table and display the "TimesheetStatusId". 0 = In Progress, 1 = Submitted, 2 = Accepted, 3 = Approved, 4 = Rejected, 5 = Pending Submit.

    If you don't use timesheets, I don't think there's an easy way to get the data except enabling the single entry mode within the server settings.


    Best regards, Julian Project Blog


    • Edited by Julian Bönigk Thursday, July 20, 2017 8:13 AM Additional Information
    • Proposed as answer by Ray Chapa Wednesday, July 26, 2017 9:31 PM
    Thursday, July 20, 2017 6:22 AM