Customized Indicators Field RRS feed

  • Question

  • I have on several occasions wished that I could extend the functionality of the Indicators field. I like that the Indicators field can show multiple different indicators for a task, unlike the graphical indicators feature, which will display only one of a limited set of indicators.

    FWIW, here’s the solution I came up with: Create a custom formula that creates a one-character string for each criterion to flag, and concatenate them together.

         IIf(Condition1,”X”,””) & IIf(Condition2, “Y”, “”) & IIf (Condition3, “Z”, “”)

    I put the formula in Text20, and use special characters in place of “X”, “Y”, and “Z”, which come from the extended portion of the character set. The formula will display all of the indicators that meet the test criteria. Here are the indicators that I normally use (based on the DCMA schedule assessment criteria, which I am often required to meet):

    ↰ Task has no predecessor
    ↳ Task has no successor
    ⇔ Task has a relationship other than finish-to-start
    ⇩ Task has a deadline
    ◇ Task has high float
    ☈ Task is a Summary task that has a predecessor or successor
    ⚓ Task has a hard date constraint (i.e. other than ASAP)
    ❎ Task is missing task data (SOW, CLIN, CWBS, or Performing Company)
    ⟽ Task has a lead
    ⟾ Task has a lag

    These indicators flag the tasks that will fail some of the schedule checks that my customers require. You can cut and paste these characters to put them into the formula, or use the Chrw() function instead.

    Friday, May 13, 2016 4:54 PM

All replies

  • TeaSeaJay,

    Thanks for sharing your solution. We did essentially the same thing using file audit macros we developed and our check criteria was based on corporate requirements rather than requirements handed down by the DCMA.

    John