    once I have submitted a timesheet I cannot modify it any more. Under which circumstance can I recall a timesheet. What will block recalling a timesheet in Project Server 2010?

    Thanks for any advice

    John


    John
    Wednesday, September 8, 2010 10:55 PM

Answers

  • Hi John,

    you should be able to recall any timesheet as long as period is not closed. A timesheet has to be recalled from "Manage Timesheet" in quick launch menu. I have checked, it does also work for approved timesheets (using default security).