  • hi every one i have add new ribbon button on Tasl list ribbon tool bar, i need to create summary task when click on it. i need to open newForm.aspx but it will be create summary task, not task. i have add new button (custtom action)with the help of SPD 2010 . Thanks
    Navaratan Sharma
    Thursday, January 12, 2012 2:36 PM

Answers

  • You can try making the summary task as the default content type and this would ensure you always create summary tasks.

    This can be done by:

    1. Go to List settings.

    2. Go to advanced settings -> Turn on - Management of content types.

    3. You will now see the list of contnet types available.

    Click on "Change order of content types". Select the content types you want and which ones should be the default ones.