  • I am using MSPDI and Interop COM to load two or more plans (all in XML format not a mpp file) and at the top i am adding a consolidated task to show the roll up of those plans.

    I am facing two issues when open the plan in 2010

    1. An active taks becomes inactive when the plan is opened in 2010. It opens perfectly in project 2007.

    2.  Some of the dropdown values are not populated in 2010 where i was able to load all drop down values in 2007

    Please help me to fix these issues.


    Thanks and Regards, Priya P