      I would like to know if it is possible to have some task to be created automatically under a project name in schedule without dates when we create a project, if yes then how that can be done?

    Wednesday, February 5, 2014 1:52 PM

Answers

  • Enterprise project template is for same. 

    IF you have a set of standard task then you can create a template on MPP then you can associate that template with EPT on Project server.

    While creating Project Template on MPP you can give a dummy date.

    From next time whenever you will create task via using that EPT all task will be available only you have to change the date and assign resource and save and publish the project.

    While creating template form MPP you have to save project as template then assign that project template with EPT on project server. 

    Once you will have MPP template these link will guide you how to create EPT.

    http://amitkhare82.blogspot.in/2011/06/project-server-2010-enterprise-project.html

    http://ntrajkovski.wordpress.com/2012/06/26/enterprise-project-types-in-ms-project-server-2010/ 


    kirtesh


    Wednesday, February 5, 2014 2:17 PM