  • Question

  • We have the RBS informations stored in a SQL Server(2008) table. How do we bring this RBS data from SQL Server to Project Server 2010?


    Sanjeev
    Friday, August 26, 2011 9:06 PM

Answers

  • Hello Sanjeev,

    There are many ways to to update the RBS values in RBS lookup table:
    1. Manually update from PWA> Servers ettings> Enterprise custom fields & lookup table> Update the RBS (would suggest if you have limited values)
    2. By using the custom piece of code , Write a code (console app/win form) which gets the data from XML file that you can export from your SQL server table. Use the Lookup table web service & use the updatelookuptable method (I have used this method in past to create/update lookup tables using the XML input)

    http://msdn.microsoft.com/en-us/library/gg210615.aspx
    Creates, modifies, or deletes data in custom field lookup tables. UpdateLookupTables creates lookup tables and corresponding code masks if the LookupTableDataSet includes new lookup tables, modifies existing lookup tables, and deletes lookup tables that are not in the LookupTableDataSet.

    3. As far as I remember that project 2010 SDK contains sample code/utility & run the ProjTool which has Create/update lookup (Not very sure , please check if you have SDK downloaded).


    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82
    Tuesday, August 30, 2011 10:56 AM