ADF V2 - connecting multiple Activites to 1 RRS feed

  • Question

  • In SSIS, we can specify an OR or AND condition in a precedence constraint.

    How does it work in ADF V2?  In the picture below, can I assume that the Activity (sp) will be executed twice?

    Is there a way to set a precedence constraint that would set an "AND" condition so that Activity (sp) is only triggered when both Activity 1 and 2 are completed "successfully"?

    Friday, June 15, 2018 9:54 PM

All replies

  • Hi,

    The precedence constraint in ADFv2 is based on 'and' operator, which means only all activity completed successfully, the subsequent activity will be executed. So the sp activity will not executes twice.

    • Proposed as answer by VairavanS (Azure) Monday, June 18, 2018 6:32 PM
    • Marked as answer by zl34 Tuesday, June 19, 2018 9:38 PM
    • Unmarked as answer by zl34 Tuesday, June 19, 2018 9:38 PM
    Saturday, June 16, 2018 1:22 AM
  • Thanks
    Tuesday, June 19, 2018 9:24 PM