  • Hi,

    I have migrated our Project 2007 to Project 2010 as part of our Sharepoint 2010 upgrade process.  On of the things we need to do is to build a Timeline dashboard to display key taks/milestones.  The options I have found thus far is from the following blog:

      http://blogs.catapultsystems.com/epm/archive/2010/01/21/creating-a-dynamic-project-timeline-using-visio-services.aspx

    This options works.  The only issue I have with this is that I have to create one ODC files for each project.  I need to know if there is a way for the end user to select the project, say from a dropdown list, and the timeline will redraw?  I am new to Project so I am looking to you experts for guidances. 

    Thanks in advance.

     

     

     

    Sunday, December 4, 2011 2:36 AM