  • My project is completely flipped. When I want to begin my project is when it ends and when it is supposed to end is when it begins. Once I entered the Predecessors and clicked sort by start date it did this, and to manually change all my start dates will take forever and  I am not eve sure when they would start. Can someone please help me?!
    Saturday, January 21, 2017 11:59 PM

All replies

  • Try inserting a column called ID and sort by it. That should set it back to how you built it initially.

    Cheers,

    Prasanna Adavi, Project MVP