Does the Azure Stack TP3 POC have like a "Time limit" or "Time Bomb" that after a few days the environment doesn't run anymore? If yes, for how many days does the azure stack poc run?
Provided it has been connected to the internet at least once so the VMs can activate,it lasts for 180 days as it uses eval copies of Windows Server. If it hasn't been connected to the internet, ever it'll last 10 days as that's when the timeout window
is for eval copies without activating.