none
MS Project, clearing baseline for selected tasks RRS feed

  • Question

  • MS Project 2007 SP2

    In a project, I want to cycle through all the tasks and based on criteria, execute the BaselineClear method. This method seems to only be available in the Application object, not at the Task object. That forces a workaround where each task needs to be selected with the SelectRow method. The problem there is if the user has collapsed rows or filtering, the VB code now has to turn off the filtering and uncollapse the rows.

    This seems very kludgy. Is there a better way to clear baselines when the Task is selected through the ActiveProject object?

    • Moved by billb08 - MSFT Thursday, November 18, 2010 5:32 PM better to assist in answering (From:Visual Basic for Applications (VBA))
    Tuesday, November 16, 2010 1:52 PM

Answers

All replies