Cost Resource Type RRS feed

  • Question

  • Hi all,

    Do you know why Microsoft just provide the types Work and Material? Ok, there is another "NotSpecified"... Why isn´t there Cost?

    The context is Project Server 2013, not 2010. And the question is relevant for the library that Microsoft provide Microsoft.ProjectServer.Client

    http://msdn.microsoft.com/en-us/library/microsoft.projectserver.client.enterpriseresourcetype_di_pj14mref.aspx

    Thanks!
    • Edited by Miguel Soler Wednesday, July 24, 2013 12:34 PM missundertood
    Wednesday, July 24, 2013 11:00 AM

All replies

  • There is a cost-type resource - it's accessible from the Client and via VBA:

    Wednesday, July 24, 2013 12:19 PM
  • Andrew,

    I have edited my original post. Do you get now my idea?

    Thanks!

    Wednesday, July 24, 2013 12:35 PM
  • Cost resources may not be edited from the PSI.  They're only accessible via the Project Pro client - or they were in 2010.  Can't remember if 2013 is any different, but I doubt it.

    Conclusion: they're not as accessible from code as material or work resources are.


    Andrew Lavinsky [MVP] Blog: http://azlav.umtblog.com Twitter: @alavinsky

    • Proposed as answer by Kashif Nizam Friday, July 26, 2013 1:16 AM
    Thursday, July 25, 2013 2:18 AM
    Moderator