Task Duration Changes on Project Sync with SharePoint RRS feed

  • Question

  • Okay, here's an easy one...

    Why do task durations change when I sync my project with SharePoint? More importantly, how do I keep this from happening?

    For example: In Project I will have a task that has a 1 day duration. After syncing it with SharePoint that task then says 0.75 days.

    I am using Microsoft Project Professional 2016 and SharePoint 2013.

    Thanks for your help!

    -J


    JFitch

    Monday, October 24, 2016 5:01 PM

All replies

  • A little more on this...

    The problem seems to track with the time changing on the tasks. 

    If I ensure that the time zone on SharePoint and the time zone on my computer match, should this prevent this from repeating?


    JFitch

    Wednesday, October 26, 2016 11:05 PM