  • Hi,

    I am facing an issue with Ms Project Server 2010 for approval of Task Updates. User has marked the Task as completed and send the status update to Manager. Manager has approved the Task Update and published the schedule. However, the project schedule doesn't display the Task as complete.

    I have also checked the Task History page of Approval Center. The Task History page displays that the Task was Approved as Completed and the schedule was published. I am unable to get a resolution for this issue. Any help in this regard will be appreciated.

    Friday, January 30, 2015 3:16 PM

All replies

  • Hi,

    please check the task type. I assume this task has Task Type fixed Duration. Because of that, the assignment is complete, but task is not.

    Does that explain what you see?
    Regards
    Barbara


    To increase the value of this forum, please mark the replies that helped to solve your issue as answer. If you find answers to questions from other forum participants to be helpful, please mark them as helpful. Your participation will help others to find an appropriate solution faster. Thanks for your support!

    Saturday, January 31, 2015 5:29 AM
    Moderator
  • The issue is there for both Fixed Units and Fixed Duration type of tasks. More details of the issue:

    a. User has updated only the Actual Start and Actual Finish Dates and sent the updates for approval. The issue does not appear when actual work or remaining work is updated

    b. While approving the Task Update, the previous Actual Date is displayed in Preview screen is incorrect. The year displayed is 2147

    Is this a known issue for updates by Actual Start Date and Actual Finish Date?