Add lines warning message project server 2007 : Timesheet lines were not added because at least one of them already exits. RRS feed

  • Question

  •  

    All of the assignments the team member is assigned are listed in Add Lines by project. If the assignment exists in the Timesheet and the user attempts to add the same assignment without selecting a unique classification the following warning message appears: Timesheet lines were not added because it already exists. The Server Side Scheduling engine recognizes the assignment as a duplicate and does not allow it to be added to the Timesheet.

    How can we check if an assignment is already exists in the timesheet?

    How can we ignore that particular assignment which is already exists instread of not adding any of the assignment which doesnt exist? 