Project Server behaving weiredly RRS feed

  • Question

  • Hi Guys,

    Task 1      1st May 2018     27rd July 2018

    Let me explain with a scenario, I have change the  finish date of a task say for ex. Task 1 to 20th July from PSI, the dates get incorrectly updated in the (dbo,draft & in pub) schema of project server database but it is consistent ie., means the dates in all the schemas are same. The values of dates became 19th July 2018 to 9th Oct 2018

    Now the problem is when I open the same project in Professional, the dates are the one which I had changed through PSI i.e., 1st May 2018 to 20th July which is correct. Why is this behaving this way, Is this a bug in Project server ?

    Note: Am using Project Server 2013, the task type had ASAP constraint before change and after change it became Finish No earlier then

    Thanks,

    Amit

    Monday, October 17, 2016 11:30 AM