Querying Work Items not linked to a Parent Work Item RRS feed

  • Question

  • In Visual Studio Team Foundation Server 2013, I'm trying to create a query with the query editor that shows tasks not linked to a solution requirement. How would I do this?

    Both task and solution requirement are work item types. If they were linked, the solution requirement would be the parent for a task.

    Thanks.

    Thursday, July 10, 2014 9:18 PM

Answers

  • Select a "Work Item and direct link query" and set option "Linking filters" to "Only return items that do not have the specified links" for types of links "Parent"