none
Project Center & My Task Grid RRS feed

  • Question

  • Hi,

    I have a VBA which writes into Text3 & Text4 Field in the project plan. 

    The Macro works just fine. but when i see these fields in My Task in the My Assignment view it does not show the data. where in project detail grid it shows the data in Text 3 & 4 column.

    Why this is happening??


    Thanks, Parth

    Tuesday, April 16, 2013 6:45 AM

All replies

  • Hi,

    I guess that your custom fields are Task fields.

    In that case, you have to check that the button Calculation for Assignment Rows is set to Roll down, unless manuelly specified.

    Otherwise, the custom fields would be defined only at the Task level, and not on the assignment level.

    Hope it helps,

    Sylvain

    Tuesday, April 16, 2013 9:36 AM