  • Hi,

    As of now, We are using visual studio 2013 ultimate for load test and running the test project from local machine. Now, we need to do the same from one remote machine. But in that remote machine, we don't have visual studio 2013 ultimate.

    Please let me know if we have any possible ways for this task.


    -Sugumar Panneerselvam

    Thursday, December 31, 2015 7:07 AM

Answers

  • Hi Sugumar Pannerselvam,

    If you want to run the load test remotely, we would install the test controller and test agent.

    For example, two machine A and B.

    A: VS, load test project, test controller.

    B: Test agent.

    So if you run your test remotely, the test controller will send messages to the test agent, the test agent will call the mstest to run your tests.

    https://msdn.microsoft.com/en-us/library/ff400223.aspx

    Note: To run the test remotely, we would edit the .testsettings file, I think you could get useful information in above link.