  • Question

  • In My Tasks we are using a version of the My Assignments view with Actual Work and Remaining work included in the view.  We would like to these to display in hours not in days, which apparently are the default. We are using PS2007 and I have Admin Access.  How do we change this to hours?
    Thursday, March 3, 2011 9:27 PM

All replies

  • There should be a little drop down in the top right of the webpart that allows
    you to edit the webpart settings.  In there, there's a setting to flip it
    from days to hours.
     
     

    Andrew Lavinsky [MVP] Twitter: @alavinsky
    Thursday, March 3, 2011 11:04 PM