Using UpdateProjectProperty to update a multi value project server custom field RRS feed

  • Question

  • Does the Microsoft.Office.Project.Server.Workflow.UpdateProjectProperty allow updating of a multi value Project Server custom field?

    Is this supported at all? If so, should the CodePropertyValue be used or another?

    Thanks

     

    Monday, August 8, 2011 4:21 AM

Answers

  • Hi graydenh,

    Yes, the UpdateProjectProperty workflow activity allows you to update a multi-value custom field.

    For a multi-value project custom field, the UpdateProjectProperty activity will add the value to the selected values, so previously selected values are not deselected.

    You can also only add one value at a time using the UpdateProjectProperty activity. So if you need to specify multiple values, you need to have multiple UpdateProjectProperty activities in your workflow.

    I hope this helps,
    Hans


    My EPM blog: Projectopolis
    Monday, August 8, 2011 9:59 PM