Grouping projects into programs(project server 2010)

Question
-
Please is it possible to group projects in the project centre into different programs( a collection of realated projects)
how can this be acheived?
Tuesday, October 19, 2010 2:55 PM
Answers
-
kehinde Bada --To do this, your Project Server administrator should create a custom enterprise Project field that lists the names of your company's programs. Then each PM will need to select a value in this field using the Project Information dialog each time he/she creates a new project. Then the custom field would need to be added to a default or custom Project Center view with grouping applied to that field. Hope this helps.
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"- Proposed as answer by joommie Wednesday, October 20, 2010 11:09 AM
- Marked as answer by Christophe FiessingerMicrosoft employee Friday, October 29, 2010 3:11 AM
Tuesday, October 19, 2010 2:59 PM
All replies
-
kehinde Bada --To do this, your Project Server administrator should create a custom enterprise Project field that lists the names of your company's programs. Then each PM will need to select a value in this field using the Project Information dialog each time he/she creates a new project. Then the custom field would need to be added to a default or custom Project Center view with grouping applied to that field. Hope this helps.
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"- Proposed as answer by joommie Wednesday, October 20, 2010 11:09 AM
- Marked as answer by Christophe FiessingerMicrosoft employee Friday, October 29, 2010 3:11 AM
Tuesday, October 19, 2010 2:59 PM -
Thanks alot dale
This actually solves it
Thursday, October 21, 2010 11:06 AM -
kihinde Bada --You are more than welcome, my friend!
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"Thursday, October 21, 2010 1:18 PM