Need to Get In progress planning window tasks in programetical way RRS feed

  • Question

  • thanks for this reply ... I am in another trouble .Here I need to show those tasks that comes in Planning window (In progress) view for My Tasks .... what is the logic behind to get those tasks or any other programmatically way to find those tasks

    Regards

    Piyush


    piyush mishra

    Wednesday, July 30, 2014 5:40 AM

Answers

  • Hello,

    You wont get the exact code Microsoft use but you will have to play with the logic until you match that view. What is missing / different from your view? Just update the code / logic to include / exclude those tasks that are missing / including.

    I can't give my work email address as this forum isn't for generating work leads etc. I would contact your local Project and Portfolio Partner if you need support / consultancy with Project Server development if this forum isn't helping. The link to pinpoint is below:

    http://pinpoint.microsoft.com/en-GB/companies/search?q=Project

    You might need to update the location etc.

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS

    Monday, August 4, 2014 12:30 PM
    Moderator

All replies

  • Hello,

    This will include any tasks that fall in the current period (defaults to current week) but also tasks from previous periods that are not complete.

    Where are you getting the task information from? What is the purpose? A report? New interface for users to submit time?

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS

    Wednesday, July 30, 2014 7:35 AM
    Moderator
  • Hello Paul ,

    Thanks for reply ...As  you said ,yes I have to provide custom interface for task update..SO I need those task that comes in planning window : in progress ....... I get task information from Statusing service data set so guide me for this current period concept and all that and how to get this settings from EPM to get in progress task of planning window:

    Regards

    Piyush


    piyush mishra


    • Edited by Mratunjay Friday, August 1, 2014 5:47 AM
    Friday, August 1, 2014 5:46 AM
  • Hello,

    The logic would be something like:

    where assignment is within the current period (usually as week) or the assignment date is before the current week and the assignment is not 100% complete.

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS

    Friday, August 1, 2014 8:09 AM
    Moderator
  • Hi Paul 

    Yes i have done the same thing ....... still planning windows gives some wrong result.....Please guide me...or Give some links about the forum which have similer stuffs in terms of codes

    it is good if you share your any mail ID for communication ...because i am new in Project server development....

    Regards

    Piyush


    piyush mishra

    Monday, August 4, 2014 10:19 AM
  • Hello,

    You wont get the exact code Microsoft use but you will have to play with the logic until you match that view. What is missing / different from your view? Just update the code / logic to include / exclude those tasks that are missing / including.

    I can't give my work email address as this forum isn't for generating work leads etc. I would contact your local Project and Portfolio Partner if you need support / consultancy with Project Server development if this forum isn't helping. The link to pinpoint is below:

    http://pinpoint.microsoft.com/en-GB/companies/search?q=Project

    You might need to update the location etc.

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS

    Monday, August 4, 2014 12:30 PM
    Moderator
  • Hi Mather

    i need impersonation in project server 2013 using PSI to get projects of PWA currently loggedIn user using Read project status method but impoersonation is not working on this approach ...plz help me on this it is urgent

    Regards

    Piyush


    piyush mishra

    Saturday, August 30, 2014 1:49 PM