Changing Working Time Project Professional 2010 RRS feed

  • Question

  • Hi

    I'm trying to change the working week for a resource (from 5 days to 3 days) from within Project Professional 2101, but when I click on the text box in the "Exceptions" tab of "Change Working Time" it won't let me type. My resources are help in Project Web Server and I think I have to check the resource out to my project, but I can't seem to find a way to check the reource out to my existing project (when I "open" from within PWA it fires up a new project in PP2010.

     

    Many thanks

    Wednesday, August 17, 2011 3:40 PM

Answers

  • Craig --

    Navigate to the Resource Center page in PWA and select the resource whose calendar you want to edit.  Click the Open button to open the resource in the checked out Enterprise Resource Pool.  Double-click the name of the resource and then click the Change Working time button.  You should now be able to change the working calendar for the resource.  Click OK and then click OK again, and then save and close the Enterprise Resource Pool.  Hope this helps.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Thursday, August 18, 2011 3:33 AM