Powershell- Resource assignement specifc task RRS feed

  • Question

  • We found powershell sample to create/update task in powershell but how create/change assignement for specific task?

    The main goal is to update a specific project with data coming from other planing to have a global vien on the resources plan and work load.

    Wednesday, April 30, 2014 7:32 AM

All replies

  • Assuming with powershell you are actually calling respective project server web services to perform the operations, There are several things that PSI doesn't do, read here - http://msdn.microsoft.com/en-us/library/office/ee767706%28v=office.15%29.aspx#pj14_WhatPSIDoes_DoesNotDo However if i am understanding correctly from what you want is to update the Assignments, correct me if i am wrong, if yes then you would need to use the Statusing service and update the assignments details example can be found here http://msdn.microsoft.com/en-us/library/office/gg209876%28v=office.15%29.aspx

    Thanks | Sunil Kr Singh | http://epmxperts.wordpress.com

    Monday, May 5, 2014 6:37 PM
    Moderator