    I am working with MS Project 2013 and Project Server 2013.

    I need to the send email notification to the program manager (or to a user) whenever the project manager changes the task finish date for a task. Comparison should happen with the baseline finish and the difference needs to be updated to the Program Manager over mail.

    How to configure/customize email notification for changes in MPP.

    Please suggest.

    Regards,

    Sudhir
    Thursday, December 4, 2014 11:04 AM

All replies

  • If you are not having developer skills it will be complicated for you.

    You need to create event handler by code, as in the below link:

    http://msdn.microsoft.com/en-us/library/office/gg615466%28v=office.14%29.aspx

    Then compare your values and finally send email by code.



    Twitter : @MShoubaki | http://jo.linkedin.com/in/mshoubaki

    Monday, December 8, 2014 10:22 PM