Can we roll up Task Custom field value to the summary task. if yes, how can we acheive that. RRS feed

  • Question

  • Can we roll up Task Custom field value to the summary task. if yes, how can we acheive that.
    Monday, May 2, 2011 6:12 AM

Answers

  • Hi,

    you haven't mention what version and if it is a locale or an Enterprise field, so a quite generic description: In your field definition dialog, there is an option "Calculation for task and group summary rows"/"Calculation for Summary Rows". Activate this and select your calculation options.

    Hope that helps?
    Barbara