  • Hi,

    We wanna know if someone fix this type of problem we got at this time.

    Regular workers here make their timesheet every week.

    Some managers changed values from timesheet of regular workers by project pro.

    We wanna block or validate and don't let pass some alteration on save event of project pro.

    Did someone made this type of change ?

    I know that he can developed in VBA but the solution it's not great because we will have to deploy this solution on every client.

    If possible, we wanna make this type of validation on server side.

    Thank you.

    Stephen C.

    Monday, August 31, 2015 1:42 PM

Answers

  • Hello,

    If I have understood your query correctly, why don't you just enable "Only allow task updates via Tasks and Timesheets." in PWA Settings > Task Settings and Display > Protect User Updates. This will stop user making changes to actual work in projects manually.

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS | MVP | Downloads

    • Marked as answer by SittButt Tuesday, September 1, 2015 11:51 AM